Concept
Default Rules at Law and Equity
Time for performance
Default Rules at Law and Equity
A closing date passes and one side has not performed. How much does the miss matter? The answer starts with a split between two forums. At law, failing to perform on the agreed day is a breach. In equity, no breach is deemed to occur until performance becomes unreasonably late. Lawyers compress the split into a formula: time is always of the essence at law unless the parties expressly agree otherwise, but time is not of the essence in equity unless the contract or the surrounding circumstances make it so.1
The two forums also give different relief. A court of law awards money damages. A court of equity can order a party to do what the contract promised, which in a land sale means specific performance: a decree compelling the seller to convey or the buyer to pay and take the land. Land makes the equitable remedy the natural one. Each parcel is unique, so damages are presumed inadequate, and a party seeking specific performance of a land contract need not offer special facts showing that the legal remedy falls short.2 When a closing date slips, the working question is often whether equity will still order the sale completed.
These rules are defaults. They govern a missed date when nothing has made time essential, and the next section explains how a clause, the surrounding circumstances, or a notice can change that. A second, later test asks how serious a failure to perform is. The Restatement (Second) of Contracts lists its factors: the benefit the injured party loses, how well money can make up for that loss, the forfeiture the late party would suffer, the likelihood that the late party will cure, and the late party's good faith.3 The defaults come first because they set the starting point: what a missed date means before anyone has made time essential.
Time at Law
A contract that fixes a closing date promises performance on that date, so a party who misses it has broken the promise at law, however short the delay. That is the force of the traditional statement that time is always of the essence at law unless the parties expressly agree otherwise.4 The statement is a fair guide to whether a breach occurred. It misleads about what the breach does.
Despite the phrase “of the essence,” lateness alone is not fatal. Unless time has been made of the essence, the delay is a nonmaterial breach, one not deemed sufficiently “total” to let the injured party rescind or abandon the contract.5 The distinction between a covenant and a condition holds both ideas together. A covenant is a promise, and breaking it creates liability. A condition is an event that must occur before the other party's duty to perform arises, and its failure frees that party. Strict performance on time is a covenant, but it is not a condition of the other party's duty to perform.6
The policy is practical. Moderate delays are common in real estate sales, and they are rarely so harmful that they justify discharging the injured party from the contract's duties.7 Damages answer the real grievance, which is the cost of the delay itself. An exam answer that lets the buyer cancel just because the seller closed late is therefore wrong when nothing has made time essential.
Those damages are narrow. A tardy seller might owe lost rents or profits the buyer was forced to forgo, and conceivably higher interest on the buyer's mortgage loan if rates rose during the delay. A late buyer might have to reimburse the seller for interest and taxes paid while waiting.8 But delay often saves the injured party money as well as costing it, and courts usually offset those savings against the damages. The net recovery can shrink very materially, so claims for delay are often small or nominal and rarely brought.9
The axiom that time is always of the essence at law overreaches in one more respect. Authority is thin, but the few cases that address the late party's own claim award that party damages, and courts are likely to follow them.10 That result runs counter to the axiom, which on this point is simply overbroad and inaccurate.
Time in Equity
Equity treats the closing date with more patience than the damages action does. In equity, time is not of the essence in a contract for the sale of land unless the contract specifically so provides or special circumstances surrounding its execution so require. When time is not of the essence, equity allows a reasonable time for performance.12 Making time of the essence turns the stated date into a firm deadline. Without that step, the date is a target, and a party who tenders within a reasonable time after it can still obtain a decree compelling the other side to complete the sale.
Two supports hold the rule up. The first is how closings actually happen. Many unavoidable delays occur in real estate sales, and the buyer needs time to obtain financing, inspect the property, and secure government permits.13 The second concerns the remedy. Land is unique, so damages are assumed inadequate, and the party seeking specific performance need not prove otherwise.14 Specific performance would be hollow if a missed date by itself could destroy it.
A court should refuse to let the seller rescind and should grant the first buyer specific performance. Setting a closing date does not make time of the essence, and nothing else in the contract does either. Unless circumstances indicate that timing is critical, the buyer has a reasonable time to close. The two-week delay came from factors beyond the buyer's control that were clearly foreseeable in the contract, so it is reasonable.15 The higher offer does not change that analysis.
The rule protects a late seller as readily as a late buyer, because it limits the consequence of lateness for whichever side happens to be late.
The late party's right to a decree depends on readiness within a reasonable time, and how long that lasts depends on the circumstances. A buyer cannot rescind the moment a title or physical defect comes to light, because the seller has time to rectify or remove it. A seller may even have time to bring an adverse possession suit without breaching the contract by unreasonably delaying closing.16 The word “unreasonably” marks the boundary: equity tolerates delay from causes the contract anticipates, but it does not tolerate delay that has no good explanation.
Reasonable time also fills the gap when the agreement names no closing date. Performance is then implied to be due within a reasonable time, and what is reasonable is a question of fact.17 A court that decrees specific performance of such a contract may fix the date itself, as one court did by ordering a sale closed within sixty days of its decision although the agreement contained no closing term.18
The equity default can be displaced, so the first question on any exam stem built on it is whether anything made time essential. A buyer whose financing arrives two weeks after the closing date can still compel a reluctant seller to close when the contract is silent about time, but may be unable to count on a decree once the contract states expressly that time is of the essence.19 Even then, minor delay by one party is permitted when the other party suffers no harm.20 Special circumstances surrounding the contract, and a notice from the party who is not in default, can also make time essential. The next section takes up each of those routes.