Missing the closing date, by itself, rarely ends anyone's rights. Unless time has been made of the essence, a late closing counts as a breach only at law, and in equity no breach occurs until the delay becomes unreasonable.1 The breach recognized at law is real but nonmaterial, so the late party is liable in damages while the other party stays bound to the contract.2 The general test for materiality explains the result. It asks, among other things, how much of the benefit the injured party reasonably expected will be lost and how adequately damages can make up for that loss.3 Moderate delays are common in land sales, and they rarely hurt the party who is ready to close (the ready party) enough to justify discharging it from the contract.4
Three situations follow from that starting point: what the ready party can recover, what the late party can still enforce, and what happens when neither party appears on the closing date.
Damages Without Cancellation
The ready party can recover only for the harm the delay itself caused. If the late party never performs at all, damages may expand to loss of the bargain, but if performance is tendered within a reasonable time, damages are limited to harms resulting from the delay per se.5 A late seller may owe the buyer the rents or profits the buyer was forced to forgo, and conceivably the higher interest on the buyer's mortgage loan if rates rose during the delay. A late buyer may have to reimburse the seller for interest and taxes paid during the delay.6 A late closing often saves the injured party money as well as costing it, and courts usually offset the savings against the damages, which can reduce the net recovery very materially. Recoveries are therefore often small or nominal, and they are rarely sought.7
What the ready party cannot do matters more than what it can recover. Contract law distinguishes a covenant, a promise whose breach creates liability, from a condition, an event that must occur before the other side's duty falls due. When time is flexible, closing on the stated date is a covenant but not a condition of the other party's duty to perform.8 The ready party therefore cannot rescind or abandon the contract because the date was missed, since a delay of this kind is not sufficiently total to permit that.9 The policy is easy to see from the other direction. If a few days' lateness let the ready party walk away, any party whose bargain had soured could use the slip as an excuse to escape, and the escape would be worth far more than the delay cost. The law therefore confines the ready party to damages. A clause making time of the essence changes this, and the next section takes up that case.
Enforcement by the Late Party
A nonmaterial breach does not strip the late party of its own right to enforce the contract. Where time is not of the essence, a party who performs or tenders within a reasonable time can still obtain specific performance.11 Suppose closing was set for July 1 and the buyer tenders the price on July 2. The buyer can presumably still secure a decree compelling conveyance, but the buyer is liable to the seller for the actual damages the delay caused, such as the interest the seller lost on the sale price.12 The seller cannot answer the tender with a refusal, because tardiness that is not unreasonable does not excuse the other party from performing.13
The same logic gives the late party a choice of remedies when the ready party repudiates. If the other party refuses to perform at all, the late party can plainly get specific performance, and if it prefers damages for total breach there seems no reason to deny them. Authority on the point is sparse, but the few decisions award the late party damages and are likely to be followed. That result runs against the axiom that time is always of the essence at law, and on this point the axiom is simply overbroad and inaccurate.14
The protection lasts only while the delay stays reasonable. Equity finds no breach until performance becomes unreasonably late, and the rule that tardiness does not excuse the other party carries the same qualification.15 A seller who must cure a title defect shows how the limit works. When time is not of the essence, the seller's time to cure may extend for a reasonable time beyond the closing date. When time is of the essence, the seller must cure by the closing unless the buyer gave inadequate advance notice of the defect or waived the marketable title requirement.16 Whether a particular delay has gone beyond a reasonable time depends on the circumstances, including how likely the late party is to cure and whether it has given reasonable assurances that it will.17
When Neither Party Tenders
A different posture arises when the closing date comes and neither party tenders. Each side's duty to perform depends on the other's tender, so neither party has done anything the other can call a default. If time is not of the essence, neither party is in material breach, and the closing is automatically extended until one of them sets a new date and gives the other notice a reasonable time in advance of it.19 An automatic extension fits these facts because both sides stayed away, often for the same routine reasons of lender processing and title work, and there is no basis for blaming one of them. The extension is not open-ended, however. A party who is ready to close can fix a firm date by naming one and giving the other side reasonable advance notice.
The analysis changes when time is essential and neither party tenders. A court might follow the same automatic-extension approach, or it might treat both parties as discharged on the ground that a condition to each one's duty has failed, and the parties' intent, as shown by their actions and the surrounding circumstances, can guide the choice.20 That uncertainty is one reason the next section treats essential time on its own.