Materiality of Delay
A closing date passes without performance, and the first question is how much the lapse matters. The earlier sections gave land-specific answers. The general contract test is Restatement (Second) of Contracts § 241, which lists five circumstances that are significant in deciding whether a failure to render or to offer performance is material.1 A court asks how much of the expected benefit the injured party will lose, how adequately that party can be compensated for the loss, how much forfeiture the late party will suffer, how likely the late party is to cure (taking account of all the circumstances, including reasonable assurances), and how far the late party’s behavior comports with good faith and fair dealing.2
Materiality decides what the injured party may do. Any breach that causes foreseeable harm supports a claim for damages, material or not.3 Only a material breach, one significant enough that the injured party may treat it as total, excuses that party from further performance.4 Because each side’s duty depends on the other side’s performance being substantially fulfilled, a minor breach leaves the injured party bound to perform. It may set off its damages, but it must still pay the net amount due.5 A party who answers a minor breach by withholding performance therefore becomes the material breacher.6
For land sales, that rule has a practical edge. A seller who cancels over a short, harmless slip, or a buyer who refuses to close because the deed arrives a few days late, has bet that the delay was material, and loses the bet if the court disagrees. The five circumstances decide the bet, and they do not add up to a formula: each is important, none is conclusive, none necessarily favors one party, and they often contradict one another.7 Each cuts in a fixed direction:
- Deprivation of expected benefit: the greater the loss, the more material the delay.8
- Adequacy of compensation: the less adequately damages can repair the loss, the more material the delay.9
- Risk of forfeiture: the more the late party would lose if the contract ended, the less material the delay.10
- Likelihood of cure: the likelier the cure, the less material the delay.11
- Good faith and fair dealing: the worse the late party’s conduct, the more material the delay.12
The subsections below take the circumstances in that order and test each on land-sale facts.
Deprivation of Expected Benefit
The first circumstance asks how much of the benefit it reasonably expected the injured party will lose, and materiality rises with the loss.13 Typically it is the most important of the five, because it asks whether the performance fulfilled the essential purpose of the contract, so that the injured party substantially received what it was entitled to expect.14 The other circumstances do not speak to that core. They are equitable considerations that a court weighs once it has measured the deprivation.15
When the severity of a breach is not obvious, a court considers the whole exchange and asks whether the missing or defective performance forms a significant part of the consideration the injured party bargained for. The crucial question is whether the breach will deprive the injured party of its reasonably expected benefit of the bargain.16 The word reasonably ties the inquiry to what the contract entitled the injured party to expect, and the parties’ own words count. If the contract states that failure to pay exactly on time will be a material breach, a court will likely give effect to that statement. If it does not, the court examines the nature and purpose of the contract to decide whether the delay matters.17
A lease shows a delay that deprives the injured party of almost nothing. A tenant must pay a security deposit by a stated time and pays about seventeen hours late. The provision exists to put the security in the lessor’s hands before the lease begins, and there is no obvious reason why seventeen hours fundamentally impairs the lessor’s benefit of its bargain. Without a clear statement that exact timing is material, the delay should not be treated as material.18
A late insurance premium shows the opposite. In 21st Century North American Insurance Co. v. Perez, the court of appeals held the late payment material because timely payment of the premium was a material term of the policy. Timely payment went to the root and essence of the contract, and letting an insured pay late would create chaos in the insurance industry and undermine an insurer’s ability to control its exposure to liability. The case also illustrates the tie between material breach and strict compliance with an express condition.19 The lessor lost almost nothing by waiting, while the insurer’s bargain depended on the date. The difference lies in what the date did for each contract.
Land closings usually resemble the lease more than the policy. Suppose a land contract sets a closing date and the closing slips two weeks for reasons beyond the buyer’s control that the contract clearly foresaw. A court should refuse to let the seller rescind and should grant the buyer specific performance. Many unavoidable delays occur in real estate sales, time ordinarily is not of the essence absent an express stipulation, setting a closing date does not make it so, and the two weeks’ delay is reasonable.20 That a second buyer later offers the seller more shows only that the seller wants a better deal. The benefit a seller reasonably expects is the agreed price, and a missed chance to sell for more was never part of it.
The lease, the policy, and the land illustrations point to one habit for exam stems built on lateness: ask what the date was for before asking how long the delay lasted. The first circumstance also works with the second, and together they ask whether the aggrieved party gets substantially what it bargained for.21 Where the breach proves minor, the injured party must still perform and may set off the damages the breach caused.22 The next subsection takes up that second circumstance.
Adequacy of Compensation
The second circumstance asks how adequately the injured party can be compensated for the part of the expected benefit it loses.24 Fix the direction first: the more fully money can repair the loss, the less material the delay, and the less adequately money can repair it, the more material. The first circumstance measured what a late closing takes away. This one asks whether damages can put it back.
The reasoning turns on what a finding of immateriality leaves the injured party to do. Every breach supports damages, so the practical question is whether the injured party must keep performing while it collects them. If the harm can be recovered, performing costs little: the injured party receives the exchange it bargained for and sets off its damages against what it owes, paying only the net amount.25 If the harm cannot be recovered, being held to the contract leaves a loss that no one repays, and the case for treating the delay as material grows.
Compensation falls short in at least two ways. The harm may be of a kind that money does not ordinarily repair, such as embarrassment, which generally is not compensable.26 Or the harm may be unforeseeable, since a breach supports damages when it causes foreseeable harm.27
Land closings usually fall on the compensable side. A tardy seller may owe the buyer the rents or profits the buyer was forced to forgo, and perhaps higher interest on the buyer’s mortgage loan if rates rose during the delay, while a late buyer may have to reimburse the seller for interest and taxes paid during the wait.28 A delay often saves the injured party money as well as costing it, courts usually offset the savings against the damages, and the net recovery may shrink to a small or nominal sum that is rarely sought.29 Because money repairs that kind of harm, this circumstance points away from materiality. That is consistent with the rule, covered earlier, that where time is flexible a short delay leads to damages and does not end the contract.
Because this circumstance is the easiest to reduce to a number, a court may be tempted to treat it as the whole analysis, and Norfolk Southern Railway Co. v. Basell USA shows the error. A shipper had promised to use the railroad for 95 percent of its deliveries, and the trial court held as a matter of law that the shipper did not materially breach. The Third Circuit found that the trial court had focused almost exclusively on whether the railroad could be compensated, when the other circumstances, including whether the railroad was substantially deprived of the benefit it reasonably expected, could have supported a finding of material breach.30 A loss that money can measure therefore does not make a delay immaterial when the date served a function money cannot reproduce. A loss that is hard to measure does not by itself make a delay material either, if the injured party still gets substantially what it bargained for.
A sound answer on an exam stem handles this circumstance in three moves. It names the losses the delay itself caused, asks whether each can be measured and recovered, and carries that result into the weighing with the other four circumstances.
Risk of Forfeiture
The third circumstance asks how much forfeiture the late party will suffer.32 A forfeiture is the denial of compensation that results when a party loses its right to the agreed exchange after relying substantially on it, whether by preparing to perform or by performing.33 A buyer whose contract is terminated over a late closing is the standard case. The buyer may have paid a deposit and spent money on an appraisal and a survey, and termination takes the whole transaction, a far larger loss than the delay itself cost.
This circumstance runs against the two before it. Deprivation of the expected benefit and adequacy of compensation look at the injured party, and the worse off that party is, the more material the delay. Forfeiture looks at the late party. A court asks not only what the injured party lost but also how much hardship the breacher would suffer if termination were allowed.34 The more the late party stands to lose, the less likely the delay is material. In a contract for services, a party who will go unpaid if the court finds a material breach may deter the court from declaring one.35
Forfeiture is an equitable counterweight, and it does not measure how much of the bargain was lost. Like cure and good faith, it focuses on what will happen to the breaching party if the court finds a material breach.36 A court balances it against the first two circumstances, and it does not decide the question alone.37
The circumstance explains some leniency toward late buyers. Some courts enforce time rigidly: in Doctorman v. Schroeder, the New Jersey Court of Errors and Appeals refused specific performance to buyers who were only thirty minutes late. Other courts are somewhat more lenient, particularly when the late party is a purchaser who stands to forfeit a large earnest money deposit. Significant tardiness still costs the right to enforce the contract.38 A buyer hours late with a large sum at stake faces a loss out of proportion to the seller’s cost, and the court has reason to relent.
Decided cases show the same circumstance at work in leases and land sales. In Foundation Development Corp. v. Loehmann’s, Inc., a shopping center owner tried to evict a retail tenant with a long-term lease because the tenant paid its share of common-area charges two days late. The court held that the breach was not material, and it held that a time-is-of-the-essence clause did not entitle the landlord to terminate, because the delay was both inadvertent and trivial.39 The owner was evidently trying to get out from under a thirty-year lease that failed to provide for periodic rent increases, so termination would have handed it an escape out of proportion to the lapse.40 Comment d to Restatement (Second) § 242 explains why the clause did not carry the day: stock phrases such as “time is of the essence” do not necessarily make any delay material and are weighed along with the other circumstances.41 A land sale decision ran the same way. In ADC Orange, Inc. v. Coyote Acres, Inc., a New York decision, the contract required the buyer to make an interim payment of $250,000 “in no event later than December 31, 2001.” That language did not make time of the essence, so a payment made two weeks late was not a material breach and the contract was not discharged.42
The result differs when the parties have been clear. In Elda Arnhold and Byzantio, L.L.C. v. Ocean Atlantic Woodland Corp., the Seventh Circuit enforced a “drop dead” clause in a settlement agreement against a purchaser who missed the closing deadline by only one day and would suffer a $1.7 million loss if the contract were not enforced. The court applied a two-part test that looks to the parties’ intention and to the equitable factors.43 A drop-dead clause is the clearest evidence a drafter can offer that the parties meant a missed date to end the deal, so the intention part of the test can outweigh even a large forfeiture.
A large number attached to the loss does not by itself make it a forfeiture. In enXco’s dispute with NSP, enXco claimed an approximately $100 million diminution in the value of its properties, while NSP suffered no meaningful harm from enXco’s tardy performance. The district court nonetheless determined that enXco did not suffer a disproportionate forfeiture, because it retained title to all of the real estate and assets involved in the project and never transferred any of them to NSP.44 The definition explains why the figure was not enough. Forfeiture centers on what a party has relied on and lost in the agreed exchange, and the size of a headline number does not measure that.
Likelihood of Cure
The fourth circumstance asks how likely the late party is to cure its failure, taking account of all the circumstances, including any reasonable assurances.47 The likelier the cure, the less material the delay. The first three circumstances measure loss and hardship. This one predicts: if the contract stays alive, will the promised performance arrive?
The prediction matters because the injured party’s duty is discharged only if the breacher does not cure a material breach in a timely manner. Whether the cure is timely depends on the importance of delay under the parties’ contract and on the injured party’s ability to make substitute arrangements.48 Section 242 adds those two considerations to the § 241 list: how far further delay is likely to prevent or hinder the nonbreaching party’s substitute arrangements, and how much importance the agreement attaches to performance without delay.49
A seller’s title problem shows cure without completion before closing. Barb learns on February 1 that Sam’s title is subject to a mortgage and tells him. Sam takes no step to remove the mortgage before March 1 except to instruct the closing agent to pay it from the sale proceeds, so that Barb acquires title free of it. Barb must complete the sale. Unless the contract forbids it, a seller can normally use the sale proceeds to remove monetary liens, even though he technically gets the purchase money before transferring marketable title.50 The payoff arrangement is a credible assurance of cure, and the sale goes forward.
A time-of-the-essence clause shrinks the window in which cure counts. If the contract makes time of the essence, the seller must cure the defect by the closing, unless the buyer gave inadequate advance notice of the defect or waived the marketable title requirement.51
Cure presupposes notice. A buyer who relies on a title defect must report it to the seller and allow a reasonable time to correct it, and a buyer who sues to recover its deposit may assert only the defects it pointed out.52 The general common-law rule is similar: notice of a material breach and an opportunity to cure come before termination, and agreements often add their own notice-and-cure provisions. The reasonableness of the injured party’s conduct in communicating its grievances and seeking satisfaction is also a consideration.53
The cure must also work. The efforts at cure must produce performance in compliance, or at least substantial compliance, with the contract, and if the finished product remains significantly deficient, the failure to cure adequately is itself a material breach.54
A likely cure does not decide materiality alone, because the five circumstances are weighed together.55 If the date served a purpose that late performance cannot restore, as in the rate-lock purchase, the first circumstance can still make the delay material. Cure carries the greatest weight where the defect can be repaired within a reasonable time and the date was not the point of the bargain.
Good Faith and Fair Dealing
The fifth circumstance asks how far the late party’s behavior comports with standards of good faith and fair dealing.57 The other four measure loss, compensation, hardship, and the prospects of cure. This one looks at conduct: why the party was late and how it behaved while the date slipped. The worse the conduct, the more material the delay, and the closer the delay comes to honest difficulty beyond the party’s control, the less material it is.
A breach need not be deliberate or willful to be material, and its importance is not diminished because the breacher did not intend or want it. In balancing the equities, however, a court may give some weight to whether the breach was willful or innocent, or a violation of standards of fair dealing.58 Intent therefore tips close cases and does not decide any case alone.
At the innocent end sits the land illustration from the first subsection. A two-week delay, brought on by factors beyond the buyer’s control but clearly foreseeable in the contract, is reasonable, and a court should refuse rescission and grant specific performance.59 Nothing in those facts suggests the buyer used the wait for any purpose of its own, so this circumstance adds its weight to the side of immateriality.
Both delays last weeks, so the circumstance does not turn on duration. It turns on whether the late party was held up by something it could not control or controlled the delay and used it for its own advantage. For an exam stem, three questions organize the inquiry:
- What caused the delay, and could the late party control it?
- Did the late party tell the other side what was happening as the date slipped?
- Did the late party gain anything by waiting, such as a chance at a better price?
No circumstance decides materiality alone, and an innocent delay can still be material if it defeats what the date was for.60 Good faith, like compensation, forfeiture, and cure, is an equitable consideration that does not speak directly to how much of the bargain was lost. That is why it settles close cases without deciding cases alone.61