Concept
The Section 347 Formula
Expectation damages
The Section 347 Formula
Restatement (Second) of Contracts § 347 turns the expectation goal into a three-part measure. Subject to the limits in §§ 350 to 353, the injured party may recover damages that protect the expectation interest,1 which is the interest in having the benefit of the bargain by being put in as good a position as performance would have provided.2 The section reaches that position by adding the loss in value to the injured party of the other side's performance to any other loss the breach caused, including incidental or consequential loss, and then subtracting any cost or other loss the injured party avoided by not having to perform.3
In shorthand, damages equal loss in value plus other loss, minus cost and loss avoided. The two additions follow from the two ways a breach can hurt: it cuts off the value the performance would have delivered, and it causes losses of other kinds. The subtraction follows from the way a breach can help. An injured party who stops performing saves the expense that performance would have required, and may salvage and redeploy resources it would otherwise have committed to the contract.4 Counting only what the breach took would let the injured party keep both the award and those savings and finish ahead of where performance would have left it.
The limits in §§ 350 to 353 reach all three terms. Foreseeability, certainty, and mitigation restrict what a court will count whether the figure is a loss in value, an incidental expense, or a cost said to have been avoided, so a number that fits the formula can still be cut or excluded when the loss was unforeseeable, cannot be proved with reasonable certainty, or could have been avoided by reasonable effort. Legal policies of this kind are one reason a compensatory award can differ from pure compensation.5 The three terms follow in order, with ordinary contract examples first; the land-sales section below applies the whole formula to short-term contracts for the sale of land.
Loss in Value
The first term measures what the breach took from the promised performance itself: the loss in the value to the injured party of the other side's performance, caused by its failure or deficiency.6 A failure delivers nothing and a deficiency delivers something worse or smaller than promised, so the term reaches total and partial breach alike. In either case the loss equals the value of the performance that should have arrived minus the value of whatever, if anything, did arrive. A buyer of nonconforming goods loses the gap between the goods promised and the goods delivered; a buyer who received nothing loses the full value of the goods promised.7
Where the difficulty lies depends on who breached. When a buyer fails to pay, the seller's loss in value is simply the money unpaid, and the hard question is what the seller saved by not performing. When the seller breaches, the buyer's cost avoided is simply the money not yet paid, and the hard question is the buyer's loss in value.8 The first term is therefore easy to state when the breacher owed money and hard to prove when the breacher owed goods, land, or services.
A breacher who owed money creates the easy case. A plaintiff who has fully performed and is owed only a stated sum suffers an injury equal to that sum, perhaps with interest, and a judgment for it orders the defendant to do exactly what he promised.9 A contractor who has fully performed likewise recovers the contract price, as with any other debt.10 Money needs no appraisal. When the painter's client repudiates the $10,000 job, $10,000 of expected payment disappears, so the first term is settled at once, and the fight will be over the $9,000 of costs the repudiation saved.
A breacher who owed goods, land, or services forces the court to answer a counterfactual question: what would the performance have been worth to the injured party had the breach not occurred?11 The answer starts with the bargain. A party's expectation is the value of the performance to that party, based on the purpose of the contract as gleaned from its wording and the circumstances of its formation.12 One argument about a mining lessee's reclamation clause shows the reading at work: it assumed that parties who wrote the term into the contract meant what they said and calculated their costs and benefits accordingly.13
Hawkins v. McGee makes the promised-value benchmark concrete. The doctor, McGee, promised a "100% perfect hand," and the operation left Hawkins's hand worse. The trial court awarded only an amount corresponding to the negative effects of the surgery. The state supreme court reversed and held that the measure was expectation: the value the hand would have had to Hawkins had McGee kept his promise, minus the value of the hand in its present state.14 The comparison starts from the promise, not from the hand's condition before the surgery. A before-and-after comparison captures only the harm the operation did, while the expectation comparison also captures the improvement that never came. The same formula applies, with a smaller dollar result, if the operation had left the hand neither better nor worse, and an unpaid fee would come off the recovery.15
Proof of that value usually runs through one of two proxies, market value or the price of a substitute transaction. In principle the expectation interest belongs to the particular injured party, whatever a hypothetical reasonable party would have wanted. Markets merely help identify it, either because the market approximates the party's interests well or because it lets the party realize them through a substitute transaction.16
Under the market proxy, the court compares the fair market value of the promised performance with the injured party's actual position after the breach, and the difference is the award.17 If Shawn breaches a contract to sell his SUV to Brianna for $10,000 and the SUV is worth $12,000, Brianna recovers $2,000. In formula terms, the $12,000 is her loss in value and the $10,000 she no longer has to pay is a cost avoided, so $2,000 is her net expectation. The injured party recovers only that net figure.18
Under the substitute proxy, the injured party buys the missing performance elsewhere, and the recovery is the substitute price minus the contract price. A seller breaches a $50,000 gasoline contract, and the buyer pays a third-party supplier $60,000 to obtain the quantity in time to meet its own commitments. The buyer recovers $10,000.19 For goods, UCC Article 2 calls the substitute purchase cover and expresses the buyer's damages as the cover price minus the contract price.20 The Restatement comment treats this as the straightforward case, in which the injured party has simply had to pay an additional amount to arrange a substitute transaction.21
The substitute must come as close as possible to the promised performance, because both the compensation principle and the mitigation principle demand it. A breach victim who buys a more valuable or better-quality replacement is overcompensated, and its damages shrink to reflect the cost of a nearer substitute. The rule is not rigid. The breach victim must find a substitute, sometimes within a very short time, and the full cost of a superior replacement may still be recoverable.22
Students most often err by measuring loss in value from where the injured party stood before the breach. The first term starts from what the breacher promised, and unpaid money, market value, and the cost of a reasonable substitute are the tools that put a number on it.
Other Loss
The second term collects what the first cannot: any other loss, including incidental or consequential loss, caused by the breach.24 The first term values the promised performance itself, but a breach also produces expenses and lost gains that the performance never contained, such as money spent reacting to the wrong or profit lost on a deal that depended on the performance. If damages stopped at loss in value, those losses would stay with the injured party, who would finish below the position performance would have provided.
Incidental loss is the cost of reacting to the breach: an expense the injured party would not have incurred had the other side performed.25 A seller whose buyer refuses the goods may spend money dealing with them and reselling them. Even when the resale brings the full contract price, so that no loss in value remains, the seller recovers those expenses to reach her rightful position.26 Incidental loss therefore sits on top of the first term. A steel buyer whose seller refuses to deliver a $100,000 load when equivalent steel costs $110,000 recovers $10,000 in market damages plus properly established collateral damages, such as costs incurred in delay, and a similar result follows for real property, subject to some special variations.27
The cost of avoiding a loss belongs here too, although the avoided loss itself does not. A wrongfully discharged employee who finds a substitute job may recover résumé printing, postage, and cab fare to interviews, none of which the employee would have incurred but for the breach.28
Consequential loss reaches past the contract to other transactions or activities that depended on the promised performance. Its size turns on the injured party's own circumstances, because expectation is measured for the particular promisee and not for a hypothetical reasonable one. Two parties holding identical contracts can therefore suffer very different amounts.29
The border between the two labels is not sharp. A towing charge for a damaged car could be treated as incidental loss or as part of the cost of repair, and nothing turns on the choice as long as recovery includes the loss once and only once. The labels exist to help locate losses that might otherwise escape attention.30
The land examples that follow concern the earnest-money or marketing contract, which obligates the parties to an immediate transfer of title, is usually performed within a few months, and does not authorize the buyer to take possession before a deed passes. The seller therefore does not finance the buyer's occupancy, and the contract does not substitute for mortgage financing.31 In such a sale, a seller left holding the land bears taxes, utilities, and mortgage interest that a closing would have shifted to the buyer. Those carrying costs are incidental loss, subject to mitigation: costs the seller could have avoided by reselling with reasonable effort are not recoverable.32
A buyer who planned to develop or operate the land may claim lost profit as consequential loss, and the claim must clear three obstacles. The first is foreseeability: under Hadley v. Baxendale the lost opportunity must have been within the parties' contemplation when they contracted, a point often hotly contested. The second is reasonable certainty, where lost-profit claims often fail, because a projection of what would have happened on a venture that never began is easy to inflate and hard to check. The third is mitigation. Foreseeability is measured at contracting because that is when a seller can still price a risk or ask about the buyer's plans. A buyer who fails the certainty test is not left with nothing, since the reliance interest lets her recover her expenses and puts her as close to expectation as the evidence allows.33
Lost profit on land also risks double counting, because a parcel's market value already reflects what buyers expect to earn from it. A claim for profit has to show something the market price leaves out.
The most common error with this term is adding an item that the market-value figure has already absorbed. A seller contracts to sell land for $100,000, the land is worth $95,000 on the market at breach, and the seller will pay about $10,000 in commissions and fees to resell it. If the court starts from the gross market value, the award is $5,000, and the seller stays undercompensated unless the $10,000 in selling expenses is added, which brings the award to $15,000. If the court starts from the land's net market value of $85,000, meaning the price after selling expenses, the award is already $15,000, and adding the $10,000 again would produce $25,000 and put the seller above the position performance would have provided. Both routes reach the same figure, and the rule that recovery includes each loss once and only once forbids combining them.34 The analysis must therefore first ask whether the market value used is gross or net, and only then decide whether any expense of sale remains to be added.
Costs and Losses Avoided
The third term subtracts: damages shrink by any cost or other loss the injured party avoided by not having to perform.36 The first two terms total what the breach took, and this term returns what the breach handed over. A breach that excuses the other side from its part of the bargain also frees the injured party from spending money, parting with goods, or doing work. A cost avoided is an expense of completing performance that the injured party never has to bear. A loss avoided is value the injured party recoups from money already spent, by reselling materials or applying them to another job.37 Both come out of the aggregate loss to yield a net recovery, and each is proved differently.
Cost avoided is clearest in a builder's claim after the owner repudiates. The builder recovers the contract price less the savings from not doing the remaining work, which is the same as the price less what completion would have cost, and the rule is the same when the owner repudiates before any work begins.38 Suppose a builder is to receive $150,000 for a house that will cost $120,000 to build. If the owner repudiates before work starts, the builder avoids the whole $120,000 and recovers the $30,000 profit. If the owner repudiates after the builder has spent $50,000, the builder recovers $80,000, which is the $30,000 profit plus the $50,000 already spent, and also the $150,000 price less the $70,000 of cost still unspent. The two routes agree because money already spent is not money saved.
A cost counts as avoided only if the breach actually spares the injured party from it. An expense the injured party would have incurred only by performing, and from which it can walk away without liability, is saved. An expense it has irrevocably committed to pay is not saved, so it stays in the recovery.39
Fixed overhead is the usual trap. A breaching buyer will argue that an allocated slice of the seller's rent or management salaries is a cost the seller no longer bears. In Vitex Manufacturing Corp. v. Caribtex Corp. the Third Circuit affirmed a $21,114 award and held that overhead should be treated as part of the gross profit recoverable as damages and not as part of the seller's costs. Overhead bore no direct relationship to any particular transaction and would have been the same whether or not the seller made the contract. The court found that UCC 2-708(2), which measures the seller's damages as profit including reasonable overhead, embodied the same rule and was persuasive.40
The line follows what the breach actually changes. The marginal revenue of a contract is the additional revenue it produces, and its marginal cost is the cost of completing performance, so fixed costs already expended are not part of marginal cost and only the further expenditures that performance requires count.41
A loss avoided is a saving that arrives after the breach, through the injured party's own recovery. A builder who stops work and uses leftover materials on another job has avoided that much loss. A wrongfully discharged employee who finds a substitute job has replaced the wages the first job would have paid, and recovers only the shortfall: an employee who loses a year at $100,000 and takes a one-year job at $95,000 recovers $5,000 in lost pay.42 Payments the injured party already received under the contract, and anything salvageable, are offset the same way.43 The expense of avoiding the loss is a different item. The employee's search costs are added under other loss while the replacement wages are subtracted here.
An injured party who keeps the performance instead of reselling it still retains its value. A seller whose buyer backs out of a purchase of artwork, and who keeps the piece, retains whatever the piece is worth, and the full price would overcompensate her. That value is subtracted from the promised price.44
Land sales fold much of this term into the standard measure. A seller whose buyer defaults still holds the parcel, and a damages award leaves the seller with both the money and the land. If Brownacre is worth $90,000 and the buyer breaches a $100,000 contract, the seller limited to damages recovers $10,000, the difference between price and market value, and keeps title worth $90,000, for $100,000 in all.45 The loss is therefore the price minus the land's value at breach, which the contract-market differential in the next section captures, and deducting the land's value again would count the same saving twice. Proof of that value often comes from a later resale. Many courts accept a resale price as evidence of market value at breach if the resale occurs within a reasonable time in an arm's length transaction.46 The court in Crabby's, Inc. v. Hamilton rejected the argument that a resale eleven and one-half months after breach was too remote to be evidence of value at the time set for closing.47 A later Texas appellate court expressed concern that a resale more than a year after breach might not be sufficient evidence.48 The section on proving value at breach returns to the timing question.
A seller can also avoid a cost in the ordinary way. A broker's commission payable only at closing is never owed when no closing occurs, because it was a cost the seller had to pay in order to receive the purchase price, and the commission therefore reduces the seller's recovery.49
Mitigation reaches this term because a loss that reasonable effort would have avoided is treated as avoided. One cannot recover damages that could have been avoided with reasonable effort and without undue risk, and the victim of a breach must make reasonable efforts to protect his interests.50 The avoidable consequences doctrine, which Restatement (Second) of Contracts § 350 applies to contracts, awards damages as if the plaintiff had minimized its losses, even when the plaintiff unreasonably suffered more.51 The doctrine is plainest when a builder is told to stop. In Rockingham County v. Luten Bridge Co. the county terminated a bridge contract and told the contractor to stop work, but the contractor kept building. The court allowed the anticipated profit and the losses incurred up to the breach and denied compensation for expenditures made afterward.52 The builder in the house illustration above, who ignores the repudiation and spends another $70,000, would likewise recover $80,000 and not $150,000, because the extra spending flows from the builder's choice and not from the owner's breach.