Finding a title defect does not end the buyer's duty to perform. A buyer may rescind or refuse to perform when the seller's title is unmarketable and the seller cannot cure the defect by closing, and contracts commonly pair a title standard with a period in which the seller may cure.1 The right to walk away therefore matures only if the defect survives to the date the conveyance comes due, after the seller has had whatever opportunity the contract or the law provides to remove it.
The timing rests on what the seller promised. The seller undertook to deliver marketable title at closing, and a promise that is not yet due cannot yet be broken. A buyer who finds a lien or a gap in the chain of title weeks before closing has learned a fact about the title, and the remedy arrives only if that fact is still true at closing. A buyer who abandons the contract on discovery may turn out to be the party in breach. A buyer who tells the seller what is wrong gives the seller a chance to fix it, and many defects yield to a fix: a seller can eliminate a mortgage by repaying the debt and obtaining a release from the mortgagee.2 The law of notice and cure assigns a task to each side, so that repairable problems get repaired and only the others end in rescission.
The buyer's task comes first, because the seller's duty to cure begins only when the buyer has found a defect and reported it. The seller's task follows: how long the seller has, and what counts as a cure. Together the two tasks answer the question a title problem on an exam almost always asks. When the buyer purported to terminate, did the seller still have time to cure?
Buyer's Notice of Defects
A buyer who learns of title defects before closing must notify the seller and allow a reasonable opportunity to cure them.3 The duty falls on the buyer because the buyer holds the information. A seller cannot cure an objection that was never made, and the buyer is the one who has examined the title evidence and formed a view of it. Notice puts the problem on the table while a payoff, a release, or a correction deed can still be arranged. The duty has three parts: the buyer must examine the title, must do so within the time allowed, and must tell the seller specifically what is wrong.
When the contract is silent, the buyer does the examining. A buyer whose contract does not require the seller to furnish an abstract must search the records or procure an abstract, because a buyer cannot pronounce the title defective without examining it.4 In many states the buyer receives a title report before closing that states whether an insurer will insure the title and which specific defects it will not cover. Alternatively, the buyer retains an attorney to give a legal opinion on the state of title.5 A contract may shift the work to the seller. In Lucas v. Independent School District No. 284, the seller was to furnish an abstract, and the court held that a timely objection based solely on the buyer's examination of that abstract invoked the seller's obligation to make title marketable within the contractual time frame.6 The Uniform Land Transactions Act likewise places responsibility for furnishing evidence of marketable title on the seller.7 Because it is a model act, an exam answer should treat it as a point of comparison unless the problem says the jurisdiction has adopted it. Either way, a title problem begins with the allocation the contract or governing law has made, since a buyer who must search carries a burden that a buyer holding the seller's abstract does not.
A buyer who skips the examination shows why the duty exists. In one familiar fact pattern, a buyer signed a contract providing that title must “prove good or no sale,” with no time set for examining title and no abstract promised. An anonymous letter told the buyer that the title was imperfect, and the buyer sued the next day to rescind and recover the deposit, without searching the records or telling the seller what was wrong. The buyer lost. The contract named no period, so a reasonable time was implied for the examination, and the buyer could not pronounce the title defective without making one. Had the examination turned up a defect, the buyer's next step would have been to report it and allow the seller a reasonable time to correct it, and only if the seller failed to remedy it could the buyer pursue the deposit.8
When the contract names no period for examining title, the law implies a reasonable one.9 Contracts often replace that flexible measure with a fixed objection period. The Lucas contract gave the buyer 10 days after receiving the abstract to raise title objections and deemed any objection not made in that time waived. If the buyer objected, the seller had 120 days to make title marketable, and if the seller could not, the buyer could terminate and recover all sums paid, with interest.10 Each feature has a purpose. A clock that starts on delivery of the abstract gives the buyer a fair chance to read what the buyer is asked to object to. A short window tells the seller early what needs repair. The waiver clause gives the deadline force, because an objection that arrives late is one the buyer agreed to forgo. The Uniform Land Transactions Act sets a similar rhythm: the seller has a reasonable time to cure after the buyer informs the seller of the defect, and when the buyer gives notice within ten days after receiving the evidence of title, the seller's right to cure does not extend the time for performance under the contract.11
The notice itself must give the seller something to act on. The Lucas buyer's attorney read the abstract and wrote that record title stood in School District No. 95, that the abstract disclosed no relationship between that district and the seller, District 284, and that the seller should supply satisfactory evidence of succession. The letter called itself a formal objection to title under the contract, and the seller received it in time.12 It worked because it named the defect, tied the defect to the evidence in the abstract, said what would cure it, and invoked the contract's own procedure. The seller then let the 120 days run without attempting a cure or even discussing the objection. What the court made of that default is taken up in the next section.
The notice requirement also limits the buyer's later arguments. If the seller fails to remedy the defects, the buyer in an action to recover the deposit may assert only the defects that were pointed out to the seller.13 The limit follows from the purpose of the notice. A cure period gives the seller one chance to repair a defined set of problems, and a seller who has fixed everything the buyer named has done what the law asked. If the buyer could then produce new objections at trial, the seller could do everything demanded and still lose, and a buyer who wanted out of the deal for other reasons would have every incentive to hold objections in reserve.
A buyer who first objects at the closing table can seem to spring a trap, since the seller can do nothing about a defect first heard of that morning. In states that require notice and a reasonable chance to cure, the answer is that notice must come early enough to give the seller a real opportunity. Even when the contract makes time of the essence, meaning the parties have agreed that the closing date is strict, the seller must cure by closing unless the buyer failed to give adequate advance notice of the defect or waived the marketable title requirement.14 The lesson for the buyer is to object in writing, and in detail, as soon as the title evidence is in hand.
Seller's Time to Cure
The seller owes marketable title only when the conveyance falls due, and a buyer may not rescind a land sale contract before the time for performance arrives.16 A buyer who finds a defect midway through the contract period therefore cannot terminate on discovery. The seller has broken no promise yet, because the interval before closing is the seller's time to repair the record. In many states the buyer must also notify the seller of the defect and allow a reasonable opportunity to cure it.17 A published illustration shows the sequence. Sam and Barb sign a contract on January 1 with closing set for March 1, and on February 1 Barb discovers that Sam's title is subject to an easement. Barb may not terminate on February 1. She must notify Sam, and if Sam eliminates the easement by March 1, she must complete the sale.18
The reason lies in what a repaired title delivers. A buyer whose seller clears the defect by closing receives exactly the title the contract promised. A right to terminate on discovery would let the buyer escape a bargain the seller was about to perform in full, and a buyer whose enthusiasm had cooled would have every reason to comb the record for an excuse.
The rule yields in one case. A cure period exists to give the seller a chance to fix the title, so when the seller clearly cannot obtain marketable title, waiting accomplishes nothing, and the buyer may terminate before the closing date.19 In the other direction, the seller's time may stretch. When the contract specifies no time to remedy a defect, the parties have a reasonable time to perform or to close, and a seller may even have time to bring an adverse possession suit without breaching by unreasonably delaying closing. The buyer likewise needs time to obtain financing, inspect the property, and secure government permits, which is why a purchaser cannot rescind the moment a title defect or physical defect is discovered.20 Cure covers whatever restores marketability, whether a release from a lender, a correction deed from an earlier owner in the chain, a court decree, or a payoff. The cure that most often settles the question is the payoff of a monetary lien, because it needs nothing from anyone except the seller and a closing agent.
A mortgage is a fixed debt, and paying it extinguishes it. When a mortgage encumbers the seller's title, the buyer must notify the seller, the seller has until closing to remove it, and in practice the seller pays the debt from the sale proceeds, so a mortgage rarely defeats the sale on this ground.21 The published illustration shows how far the idea reaches. Barb discovers a mortgage on February 1 and notifies Sam. Sam does nothing before March 1 except instruct the closing agent to pay the mortgage from the sale proceeds, so that Barb takes title free of it. Barb must complete the sale. Unless the contract specifically prohibits it, a seller normally may use the sale proceeds to remove monetary liens, even though, technically, the seller receives the purchase money before transferring marketable title.22 The order of events at the closing table does not matter, because the buyer bargained for the state of title when the deed is delivered. This cure works only for debts the proceeds can retire, which is why the earlier discussion of unreleased liens treated a lien larger than the price, or one the seller will not cover, as a genuine defect.
The harder case arises when the seller has not finished the cure by the closing date. Suppose Barb notified Sam of the easement on February 1 and the easement is still there on March 1. If time is not of the essence, a court may hold that Barb is not yet released from the contract and that Sam has a reasonable time to clear his title. If time is of the essence, Sam's failure to have marketable title on the closing day entitles Barb to terminate.23 The difference comes from the way courts of equity treat closing dates. Even when the parties set a date, equity tolerates delay in closing unless the contract stipulates that time is of the essence, and students often assume that naming a date carries that force when it does not. Even when time is of the essence, minor delays by one party are permitted if the other party suffers no harm.24
A time-of-the-essence clause is the parties' own statement that the date is a term of the bargain, which is why a court that would forgive a short delay elsewhere enforces the date when the clause appears. The strict duty to cure by closing still has two limits. It gives way if the buyer did not give adequate advance notice of the defect or if the buyer waived the marketable title requirement.25 The notice rule from the preceding section thus reaches into this one, since a strict deadline binds the seller only as far as the seller was told in time what needed fixing.
Parties may replace the law's reasonable-time default with a cure period of their own, and the period then fixes when the seller's opportunity ends. The Lucas contract allowed the seller 120 days after an objection to make title marketable, failing which the buyer could terminate and recover all sums paid, with interest.26 The buyer objected on time, and the 120 days ran without any attempt by the seller to cure the defect or even to discuss the objection.27 The seller then produced the missing county board orders, all dated 1946, on the 199th day after the objection.28 The Minnesota Supreme Court reversed the judgment for the seller, because the trial court had wrongly decided that the buyer had no right to terminate. It remanded only the seller's claim that the buyer had waived rescission or was estopped from asserting it.29
A contractual period turns an open-ended reasonable time into a deadline both sides can see. The seller learns exactly how long the chance to repair lasts, and the buyer learns exactly when the right to terminate matures. A seller who uses the period can keep the deal by paying a lien or recording the missing instrument within it. A seller who lets it lapse leaves the buyer holding the remedy the contract promised for that failure, and documents produced afterward do not restore the seller's position, although a waiver or estoppel argument may still be raised, as the remand shows.
A different timing rule applies once a title dispute reaches a court. When buyer and seller litigate a title defect, the title that controls is the title as it exists at the time of final decree or judgment, and not the title the seller held when suit began.30 In Conklin v. Davi, the court cited an earlier decision that granted specific performance but denied the seller his costs because most of the evidence supporting his otherwise defective title first appeared at trial.31 A seller who waits to prove good title in court may therefore still win, but at a price. The decree rule and a contractual cure period answer different questions. The decree rule describes what a court examines when it decides marketability, which is why a seller whose title rests on adverse possession can still win a litigated dispute by proving the possession at trial. A cure period is a term the parties wrote, and Lucas enforced it by its terms when the seller let it run out unused, so an answer should not assume that a seller who ignores an express deadline can rescue the deal by curing during the lawsuit.