In July 1965, Loral Corporation received a $6,000,000 contract from the Navy to produce radar sets. The contract contained a schedule of deliveries, a liquidated damages clause applying to late deliveries, and a cancellation clause in case of default by Loral. Loral solicited bids for some 40 precision gear components needed to produce the radar sets and awarded Austin a subcontract to supply 23 such parts. Austin commenced delivery in early 1966.
In May 1966, Loral was awarded a second Navy contract for the production of more radar sets and again went about soliciting bids. Austin bid on all 40 gear components but, on July 15, a representative from Loral informed Austin's president, Mr. Krauss, that his company would be awarded the subcontract only for those items on which it was low bidder. The Austin officer refused to accept an order for less than all 40 of the gear parts. On the next day he told Loral that Austin would cease deliveries of the parts due under the existing subcontract unless Loral consented to substantial increases in the prices provided for by that agreement—both retroactively for parts already delivered and prospectively on those not yet shipped. He also demanded that Loral place with Austin the order for all 40 parts needed under Loral's second Navy contract.
Shortly thereafter, Austin did, indeed, stop delivery. After contacting 10 manufacturers of precision gears and finding none who could produce the parts in time to meet its commitments to the Navy, Loral acceded to Austin's demands. In a letter dated July 22, Loral wrote to Austin that "We have feverishly surveyed other sources of supply and find that because of the prevailing military exigencies, were they to start from scratch as would have to be the case, they could not even remotely begin to deliver on time to meet the delivery requirements established by the Government. ... Accordingly, we are left with no choice or alternative but to meet your conditions."
Loral thereupon consented to the price increases insisted upon by Austin under the first subcontract. Austin was awarded a second subcontract making it the supplier of all 40 gear parts for Loral's second contract with the Navy. Although Austin was granted until September to resume deliveries, Loral did, in fact, receive parts in August and was able to produce the radar sets in time to meet its commitments to the Navy on both contracts. After Austin's last delivery under the second subcontract in July, 1967, Loral notified Austin of its intention to seek recovery of the price increases. On September 15, 1967, Austin instituted this action against Loral to recover an amount in excess of $17,750 which was still due on the second subcontract. On the same day, Loral commenced an action against Austin claiming damages of some $22,250—the aggregate of the price increases under the first subcontract—on the ground of economic duress. The two actions were consolidated and, following a trial, Austin was awarded the sum it requested and Loral's complaint against Austin was dismissed. A closely divided Appellate Division affirmed.
View case