Concept
Recoverable Expenditures
Reliance damages
Recoverable Expenditures
Section 349 of the Restatement (Second) of Contracts gives the injured party damages based on the reliance interest and offers a sample of what that covers: “expenditures made in preparation for performance or in performance.”1 The word “including” makes the phrase a sample, not a complete list. The real test is the definition in § 344(b), which describes the reliance interest as the promisee’s interest in being reimbursed for loss caused by reliance on the contract, by being put in as good a position as if the contract had never been made.2 An outlay is recoverable if the contract caused it and it ended as a loss, whatever label the plaintiff attaches to it.
Two questions sort a plaintiff’s list of expenses: what was the money for, and when was it spent. Purpose separates outlays that carry out or prepare for the plaintiff’s own performance from outlays collateral to the exchange. Timing separates outlays that followed the contract from those that preceded it. The same test then reaches income and opportunities the plaintiff gave up, which never left the plaintiff’s pocket as cash. Two requirements run through every category. The spending must be reasonable, because the measure reimburses loss and does not reward extravagance. And something of value must actually have been wasted, because waste or loss is the basis of awarding reliance damages; an outlay the plaintiff can salvage leaves nothing to compensate.3
Performance and Preparation Costs
Money spent to carry out one’s own side of a contract, or to get ready to, is the core of reliance recovery. The label for this category is essential (or direct) reliance, because the spending rests directly on the contract and is needed to fulfill the spender’s own commitment.4 Such outlays satisfy § 344(b) with little strain: the party would not have bought the materials, paid the crew, or posted the deposit had no contract been made.5 Labor and materials on a construction job are the standard instance, as is the $1,900 that Luten spent before the County repudiated, and so is any sum the contract itself obliges the party to pay or spend.6
The breacher bears these costs because the spending is the price of being able to perform. The contract itself puts the promisor on notice of it, so the foreseeability condition that the next subsection attaches to collateral outlays has little work to do here.7 Once the promisor repudiates, spending that would have been the cost of a working exchange becomes waste. One court explained that such expenditures are not brought about by reason of the breach; they are induced by reliance on the contract itself and rendered worthless by its breach.8 They are also the easiest part of a claim to prove. What the plaintiff spent before the breach is a past fact, and the fact that profits are too uncertain for recovery does not prevent a judgment for the amount of the expenditures.9
Suppose a contractor, Al, agrees to do construction work for Mary, and Mary breaches. Al could prove expectation damages, the unpaid price less the anticipated cost of completing the work, but that may take considerable effort and expense. Al may instead elect reliance and prove the expenses he reasonably incurred in preparing to perform and performing before Mary’s breach.10 Plaintiffs commonly make that choice when they cannot prove consequential expectancy damages with reasonable certainty.11
Two limits keep this category from becoming a license to spend. The first is reasonableness: in the Dempsey boxing-match case the court allowed the club’s post-contract expenses reasonably and necessarily incurred in organizing the match, and a profligate outlay would not pass that test.12 The second is waste. A developer who promises custom software and cannot sell it elsewhere recovers its expenditures; a developer who can resell has already recouped part of the loss, and the recovery shrinks accordingly.13
Section 349 departs from an older formulation of the rule in one respect worth knowing. The older formulation, quoted in the cases, allowed expenditures in preparation and part performance when profits were too uncertain to prove, but it barred recovery of them in excess of the full contract price promised by the defendant. It admitted preparation costs only if they could fairly be regarded as part of the cost of performance in estimating profit and loss, and it deducted installments of the price already received and the value of materials on hand that would have been consumed in completion.14 Section 349 has no price ceiling. Its closing clause instead reduces the recovery by any loss the breaching party can prove with reasonable certainty the injured party would have suffered had the contract been performed.15 A flat ceiling at the price applies to every claim, whether or not the contract would have lost money, while the offset asks directly whether performance would have been a loser and puts the burden of proving it on the breacher. Courts have answered the complaint that reliance damages make the breacher an insurer by pointing to that clause. A law firm argued that a reliance verdict made it absolute surety for the costs of a highly speculative venture; the court replied that § 349 lets the breacher prove any loss the plaintiff would have suffered on performance, which avoids making the breaching party a guarantor of the venture’s success.16 The mechanics of the offset belong to the next section.
Land-sale contracts add their own remedial menu, which sets damages beside liquidated damages, specific performance, vendor’s and vendee’s liens, and restitution, so a reliance claim there is one choice among several; the real estate sections below take up the details.17
Incidental and Collateral Outlays
Some outlays meet § 344(b) even though they form no part of the agreed exchange.19 The lessees in Village Plaza spent on advertising and promotion for their leased space, and a buyer may pay for an option on adjoining land to supply parking for the building being bought.20 Each spent money because of the contract and in order to enjoy what it promised, yet none was paying the other side for anything. This category is labeled incidental (or consequential) reliance: loss or expense incurred as a consequence of and incidentally to the contract, to take advantage of the benefit expected from it.21
The label can mislead. It describes outlays collateral to the contract, and it does not describe the cost of dealing with a breach after it happens. Breach-related costs, such as consequential damages and the expense of minimizing the loss, form a separate element of damages.22 Incidental reliance is spent before any breach, because the contract was made.
A court quoting a leading authority explained that expenditures made in reliance on a contract, though not part performance of it or necessary preparation for it, may be included in damages if the defendant, when the contract was made, had reason to foresee both that they would be made and that his own breach would prevent their reimbursement. The same passage warns that such collateral losses may readily be regarded as too remote.23 The conditions exist because collateral outlays rest on the promisee’s own plans, which the promisor may not know, and the agreed price was never set to cover them. There must be a limit to protect the breacher from liability for expenses it could not fairly have expected or that were not reasonably incurred. Incidental reliance is therefore recoverable only if the breacher foresaw or reasonably should have foreseen the possibility of the expenditure, and both the amount and the nature of the outlay were reasonable. Mitigation applies as well, so the injured party must take reasonable steps to recoup what is salvageable, and the loss must be proved with reasonable certainty.24 Because the price was never meant to repay collateral spending, the contract price is the wrong yardstick for it, and foreseeability does the limiting instead. Maine Rubber International v. Environmental Management Group, Inc. allowed foreseeable reliance losses that greatly exceeded the contract price.
A gym tenant shows the conditions satisfied. The tenant leases premises, pays the deposit the lease requires, and shortly before opening spends $1,000 on advertising; the landlord then leases the space to someone else. With no credible evidence of lost profits, the tenant claims reliance. The deposit is essential reliance because it was part of the tenant’s performance obligation. The lease imposed no duty to advertise, so the advertising is incidental reliance, but it was incurred in reliance on the lease and the breach made it useless.25 A landlord who lets space to a new gym can foresee that the tenant will advertise before opening, and a modest sum for that purpose is reasonable in amount and nature. Compare the bakery deposit: it too followed the signing and was lost, but only the advertising was something the other party had reason to expect. Restitution would not reach the advertising, because it pays outsiders and gives the landlord nothing. Restitution can run lower than reliance where a reasonable expenditure confers no benefit on the breacher, which is particularly likely with incidental reliance.26 Reliance recovery is not limited to benefits the defendant received.27
Other transactions follow the same pattern. A buyer of Blackacre spent $500 on a survey and $500 on loan-application fees before the vendor repudiated, and also $1,000 on an option on adjoining land for additional parking. The survey and loan fees are ordinary preparation costs; the option is the collateral item, and the vendor’s foresight of it is what makes it chargeable.28 In the Pulford distributorship case, Pulford paid $2,500 for the distributorship, left his job, and began developing his territory, and he stopped when the grantor gave part of the territory to another distributor. The court upheld an award of his development costs, including telephone installation and office furniture, because they were not incurred in preparation for or in part performance of the contract but in reliance upon it.29
Two further conditions separate recoverable collateral outlays from lookalikes. The first is timing. Incidental reliance is incurred in consequence of having made the contract, so a loss or expense incurred in anticipation of a contract not yet formed is not included, a limit the next subsection develops.30 The second is waste. A building owner who reinforces the building so it can carry a sign has wasted that cost if the signmaker cannot obtain city approval and the only function of the reinforcement was to hold the sign; if the work also improved the building’s structural soundness, the expense may not be a waste at all.31 The example also shows why the label matters. If the reinforcement was needed to enable the signmaker to perform, it is essential reliance, but if it was only the owner’s means of obtaining the benefit of the sign, it is incidental reliance, and different rules apply to the two types.32
Pre-Contract Expenses
Reliance damages protect against loss caused by reliance on the contract, and § 344(b) puts the reference point at the position the plaintiff would have held had the contract not been made.34 Money the plaintiff had already spent when the contract was formed belongs to that starting position. Section 349 points the same way, since it lists expenditures made in preparation for performance or in performance, and there is nothing to perform or prepare to perform until a contract exists.35 A loss or expense incurred in anticipation of the contract, but before it is formed, is therefore not included in incidental reliance.36 Pre-contract outlays generally cannot be recovered as reliance, even when the breach later leaves them worthless.
The plaintiff would have spent that money whether or not the defendant ever made the promise, so the breach did not cause the waste. Charging it to the breacher would reimburse the plaintiff for an earlier gamble and turn the remedy for a broken promise into insurance for negotiation expenses.
In Chicago Coliseum Club v. Dempsey, the world-champion heavyweight boxer repudiated a contract with the club to participate in a boxing match. The club could not prove its lost profit, but the court allowed it to claim reliance damages for the post-contract expenses reasonably and necessarily incurred in organizing the match. It refused the expenses the club had incurred before the contract was executed, because they predated the contract and so could not have been incurred in reliance on it.37 One plaintiff and one breach produced both results. Dempsey’s repudiation wasted both groups of expenses, so the only fact separating the recoverable group from the unrecoverable group was the date of the contract. Drysdale v. Woerth applied the same line to a tenant whose improvements predated the renewal of the lease; the improvements could not be reliance on the renewal, though the tenant could recover in restitution the value they added to the landlord’s property. Restitution survives where reliance fails because it asks a different question: whether the plaintiff conferred a benefit that it would be unjust for the defendant to keep without paying, a remedy available even when no contract was formed.38
On a fact pattern that lists outlays with dates, the date relative to formation of the contract decides the question, and the usefulness or size of the item does not.
Not every authority follows the timing line. In Security Stove & Manufacturing Co. v. American Railway Express Co., a shipper recovered pre-contract expenses from a carrier whose failure to deliver goods to an exhibition wasted them. The English decision in Anglia Television Ltd. v. Reed states the alternative plainly: a plaintiff must elect between lost profits and wasted expenditure and cannot claim both, but one who cannot prove what profits would have been can claim the expenditure thrown away by reason of the breach.39 The court also allowed costs incurred before the contract where the parties would reasonably have contemplated that they were likely to be wasted if the contract were broken. It drew on Lloyd v. Stanbury, where a land purchaser who moved a caravan and furniture to the site in anticipation of the contract recovered those costs. The two approaches ask different causal questions. The American default asks whether the contract induced the spending, while the English approach asks whether the breach wasted spending both sides expected to be lost on breach. This divergent authority is not the American default, so the safe answer treats pre-contract costs as unrecoverable reliance and raises the contrary line only when the facts show both parties knew of the spending and expected it to be lost on breach.
Two other routes can reach pre-contract spending without disturbing the timing line. When the breacher knew the plaintiff was incurring the expenses in anticipation of the contract and had strongly indicated an intention to enter it, promissory estoppel may supply relief, because the spending is then traced to the breacher’s assurance and not to a formed contract.40 The expenses may also qualify as lost-opportunity reliance if the plaintiff could have recouped them by entering a similar contract with a third party but gave up that chance by contracting with the breacher.41 The spending came first, but the lost chance of recovering it was caused by the choice to deal with the breacher. That second route leads to the next idea, that reliance covers opportunities given up as well as money spent.
Forgone Opportunities
Section 344(b) defines the reliance interest as loss caused by reliance on the contract, and nothing in that definition confines the loss to money paid out.43 The measure returns the promisee to the position held before the contract was made, and in that earlier world a promisee who later quit a job or turned down a competing deal still has the job or the deal. Section 349’s examples of preparation and performance expenditures are illustrative, and the word “including” leaves room for this loss.44
The expectation interest does not take into account opportunity costs, the value of opportunities forgone because of the contract. An example is turning down an offer of full-time employment because one has accepted a different full-time position, and an opportunity cost is a reliance cost.45 The salary at the old job was never a gain the contract promised; the promisee already had it and surrendered it by relying on the contract.
Pulford’s award, introduced in the last section, shows the category at work. Pulford had left another employer to take the distributorship, and the award included two months of forfeited salary and the value of the medical insurance he lost, along with his development costs.46 The forfeited pay involved no outlay to anyone, yet it measures a real loss caused by relying on the contract.
A forgone opportunity is best treated like incidental reliance. It is sacrificed because of the contract and not paid to the other side, so the timing, foreseeability, reasonableness, and proof requirements apply to it. A tenant who gave up a job after signing a lease, or declined an offer of other premises on the strength of it, would have an incidental reliance claim if the loss was properly established.47
The claim is only as good as its proof, and proof is where it most often fails. In Tynan v. JBVBB, LLC, the court gave the plaintiff the opportunity to prove reliance damages. He tried to show that he had lost opportunities for employment in reliance on the promise, but he could not prove this with sufficient certainty, and he ended with no award.48 The difficulty is structural. Money already spent is a past fact that a receipt can establish, while an opportunity forgone is a counterfactual, a picture of what would have come had the plaintiff not relied. Reliance is often elected to avoid proving a counterfactual, and a lost-opportunity claim brings a smaller version of that problem back. Like every other item of damages, the loss must be proved with reasonable certainty.49 An identifiable job at a known salary can be proved. A promisee who says only that other work might have come has offered a hope, and the claim fails.